Skip to navigation Skip to content

New rapid rail outloading facility coming to Moora

5/7/2021

The Moora rapid rail outloading and rail siding extension is an exciting new phase in our network investment, as we try to get more tonnes to port quicker through our outloading projects.

Currently our network has the ability to move an average of 1.6 million tonnes (mt) of grain to port per month.

With the increasing crop size and changing harvest demands, including greater shipping demands in the first half of the year, this needs to be raised to about 2.2mt per month by 2030.

Rapid rail outloading projects are part of the solution to getting more tonnes to port quicker, Manager – Network Planning Mat Pullen said.

“The rapid rail projects will increase the steady state throughput of the supply chain and crucially build in agility to sprint and catch up when disruptions to out-loading occur,” Mat said.

Moora is the most advanced out of four planned rapid rail projects, with Brookton, Cranbrook and Broomehill also selected for these exciting developments.

There are two main aspects to the Moora rapid rail outloading project: the rapid rail loading facility and the rail siding extension.

The loading facility will consist of six, 1100 tonne (t) V-Bottom Silos, two 6000t campaign silos, a batch weigher and road grid, which is able to load trains at a rate of 1,500 tonnes per hour.

A key to the project is the 1.2 kilometres rail siding extension, which is adjacent to the main line and the bulk heads that are on the site.

This will enable 66 wagons to be filled, without having to split the train up.

“At the moment, it takes around eleven hours to load and shunt a train but when the new facility is up and running, this can be done as quickly as three hours,” Mat said.

“This delivers significant benefits to the entire network and all growers, not just Moora and surrounds.”

Execution engineering and design for the civil earthworks, drainage and rail trackwork is 85% complete with the Fixed Rail Loading Facility 70% complete.

The CBH Project Delivery team (PDG) is currently in negotiations with contractors with the major construction contracts to be awarded in August.

Environmental approvals have been submitted to the regulators, with the plan to support the project's forecasted “breaking ground” in September this year.

“Construction will not impact this year’s harvest,” Mat said.

“All going to plan, we intend to start commissioning the project in mid to late 2022, ready to outload the 2022/23 harvest.”

This investment in rail by CBH has attracted State Government funding as a high priority project, identified through the Revitalising Agricultural Region Freight (RARF) strategy.

The State Government recognised the importance of these regional infrastructure assets and has committed to fund $22 million to extend and improve the rail siding on all four projects.

CBH is planning to invest approximately $80m over the four projects, with the amount to be spend at each site dependent on the configuration of the rail loading facility and associated storage cells.

Other news

Tags for this article